Polar Night Energy

Finnish pioneer of utility-scale Sand Batteries for district heating and industrial process heat. Uses low-grade sand or circular industrial byproducts like crushed soapstone inside tall insulated steel silos.

Hauptsitz
Finland (Europe)
Gegründet
2018
Speichermedium
Sand & crushed soapstone silo (up to 600°C)
Temperaturbereich
100°C to 600°C
Technologiereifegrad (TRL)
TRL 9 / 9 (Commercial)
Energieausgänge
district-heating, process-heat
Reifegrad-Anzeige

TRL 9 von 9

Wachstumsphase: Commercial · Eigentümerstruktur: Startup

Kapital & Investoren

Seed (EUR 7.6M, April 2024, led by Jonathan Oppenheimer) + Business Finland grants

Veröffentlichte Gesamtfinanzierung: ~$8.5M USD.

Investoren: Jonathan Oppenheimer, Stephen Industries, Holdix, Turret, PC Rettig & Co. Impact

Fördermittel / Öffentliche Programme: Business Finland energy & R&D grants

Leuchtturmprojekte & Anlagen

ProjektStandortKapazitätStatusJahr / Quelle
Pornainen District Heating Sand Battery (Loviisan Lämpö) Pornainen, Finland 100 MWh(th) / 1 MW(th) Operational 2025 · pv-magazine.com
Kankaanpää First Commercial Sand Battery (Vatajankoski) Kankaanpää, Finland 8 MWh(th) Operational 2022 · polarnightenergy.com
Vääksy District Heating Sand Battery (Lahti Energia) Vääksy, Finland 250 MWh(th) / 2 MW(th) Under Construction 2027 · pv-magazine.com

Jüngste Meilensteine

2025-11 · pv-magazine.com

Lahti Energia orders 250 MWh Sand Battery for its Vääksy district heating network

Polar Night Energy is main contractor for a 2 MW / 250 MWh system using about 2,400 tonnes of local sand; on-site construction was scheduled to start in early 2026 with completion expected in summer 2027.

2025-06 · pv-magazine.com

Pornainen 100 MWh soapstone Sand Battery enters operation for Loviisan Lämpö

The 1 MW / 100 MWh unit holds about 2,000 tonnes of crushed soapstone, lets Pornainen phase out oil in its heating network and cuts the network's emissions by nearly 70%.